National Highways hits the ground for M4 landslip work

National Highways is starting work this autumn to stabilise 600 metres of embankment alongside the M4 in Wiltshire which will bring the hard shoulder back into use following a landslide.

Contractors MJ Church will move around 25,000 tonnes of earth and other material before backfilling with 19,500 tonnes of stone, locally sourced from a nearby quarry, to restore the embankment and hard shoulder.

The work is part of a larger scheme between junctions 16 (Swindon West, Royal Wootton Bassett) and 17 (Chippenham) which will also see the refurbishment of four bridges across the motorway.

Chris Hilldrup, National Highways Route Manager, said: “Many of the roads and bridges we manage were built around 60 years ago and are nearing the end of their life span, so we’re acting now and renewing them to prevent bigger problems further down the line.

“This £20m investment along the M4 in Wiltshire is a significant engineering undertaking. Once we have stabilised the embankment, we will refurbish the bridges and upgrade barriers to maintain the safety and reliability of this busy route for many years to come.”

Geotech Failure

Caption: The extent of the land slippage on the eastbound M4 in Wiltshire

Identified during routine surveys, the landslide alongside the motorway has rendered the hard shoulder unsafe and unusable on the eastbound approach to Swindon, and the verges and embankments need to be stabilised before work starts on the bridge repairs in autumn 2027.

To enable the first phase of work, the westbound carriageway between junctions 16 and 17 will be subject to overnight lane closures this month, with some overnight eastbound lane closures, and a daytime hard lane shoulder closure, required for vegetation and utilities work.

Ahead of the land stabilisation work, full westbound overnight closures (8pm-6am) will be required on 12 and 13 November to install traffic management, with two lanes running under 50mph speed restrictions until 17 February. The eastbound carriageway will continue to have three lanes running as normal.

During the two overnight closures, HGVs will be diverted via Cirencester and Malmesbury, with other vehicles using separate diversion routes.

To minimise disruption, there will be lanes running in each direction for the first phase, which will only add an extra two minutes to people’s journey times.

With contractors MJ Church, National Highways is committed to reusing as much of the landslip materials as possible during the works and also sourcing the recycled concrete from the contractors’ crushing plant near Chippenham.

Once land stabilisation has been completed, and following ongoing ecology monitoring, National Highways will set about restoring the four bridges and the upgrade of 1.3 miles of safety barrier, with a programme of work scheduled from autumn 2027 to spring 2028.

Hookers Gate bridge

Caption: Above, deteriorating concrete on the Hookers Gate bridge abutment and, below, exposed and rusting steel reinforcement on the Park Ground Farm bridge deck

Park Ground Farm bridge

The bridges carry the M4 over two local roads, at Brinkworth and Grittenham, the Swindon to Bristol railway line and a farm access road, with work focussing on refurbishment and repairs to the decks of the ageing structures.

Train services will be unaffected by the bridge repairs, and full details of the traffic management will be communicated ahead of start of work in 2027.

Mr Hilldrup added: “We’re doing everything we can to minimise disruption, by keeping lanes running in each direction for the first phase, which will only add an extra two minutes to people’s journey times.

“We appreciate roadworks can impact on people’s journeys, and in the meantime, we advise people to plan ahead and allow extra time for their journeys through the works.”

In the meantime, further details can be found at the scheme web page, and during the work, people can gain up-to-the-minute updates on National Highways' Travel Alerts web page.  

 

About National Highways

National Highways is the wholly government-owned company responsible for modernising, maintaining and operating England’s motorways and major A roads.

View our press releases online at https://nationalhighways.co.uk/press/

Traffic information for England’s motorways and major A roads is available via the website https://nationalhighways.co.uk/, local and national radio travel bulletins, electronic road signs and mobile apps. Local X services are also available at http://nationalhighways.co.uk/about-us/social-media-use/.

For further information please contact National Highways' press office (24hrs) on 0844 693 1448 and select the most appropriate option below:

Option 1: National enquiries (9am to 5.30pm) & out of hours for urgent enquiries
Option 2: North West (between 9am & 5.30pm)
Option 3: Yorkshire, Humber and North East (between 9am & 5.30pm)
Option 4: West Midlands (between 9am & 5.30pm)
Option 5: East Midlands (between 9am & 5.30pm)
Option 6: East (between 9am & 5.30pm)
Option 7: South East (between 9am & 5.30pm)
Option 8: South West (between 9am & 5.30pm)